Recent Activities of Department
Explore the latest achievements, events, and milestones of department. Stay engaged and connected with our community through this dynamic platform.
SE LASBELA CIRCLE
SE Lasbela Circle Fakhruddin Jamali reviewed the ongoing development projects in Lasbela district.
He was accompanied by Executive Engineer Roads Lasbela, Arshad Zehri. During the visit, SE Fakhruddin Jamali inspected the progress and quality of the ongoing works. On the occasion, he instructed the concerned officials to accelerate the pace of work and ensure that all projects meet the required standards of quality.
He was accompanied by Executive Engineer Roads Lasbela, Arshad Zehri. During the visit, SE Fakhruddin Jamali inspected the progress and quality of the ongoing works. On the occasion, he instructed the concerned officials to accelerate the pace of work and ensure that all projects meet the required standards of quality.
CWPP&H π’ DISTRICT KILLA SAIFULLAH
Today, 20th September 2025, Worthy CMIT Member Yasir Khan Kakar, accompanied by P&D team members Director (Development) Zhob, Rafeeq Tareen, and Engr. Amanullah Khan, visited the scheme titled βConstruction of Shaheed Lala Usman Khan Kakar Public Library and Research Center at Muslim Bagh & Construction of Dairy Research Laboratory, Muslim Bagh, District Killa Saifullah.β
The work is currently in progress, and the entire building has now reached the roof-band level.
The work is currently in progress, and the entire building has now reached the roof-band level.
SE LASBELA CIRCLE
SE Lasbela Circle, Fakhruddin Jamali, inspected the under-construction Sand Road in Uthal. On this occasion, Executive Engineer Roads, District Lasbela, Arshad Zehri, along with other relevant officials, was also present. SE Fakhruddin Jamali reviewed the progress of the ongoing development project, assessed the quality standards, and issued directives to further accelerate and improve the pace of work on the project.
CWPP&H π’ DISTRICT KALAT
Under the supervision of the Buildings Department, Communications and Works, District Kalat, various development projects are progressing rapidly. In this regard, Executive Engineer Buildings, Communications and Works Department, District Kalat, Mr. Niaz Ahmed Bangulzai, reviewed the ongoing projects.
The projects include the GOR Complex Kalat, Court Rooms Khaliqabad, BHU Khaliqabad, and Court Rooms Kalat. The Executive Engineer inspected the quality of work and directed that the pace of construction should be further accelerated while ensuring improved standards.
The projects include the GOR Complex Kalat, Court Rooms Khaliqabad, BHU Khaliqabad, and Court Rooms Kalat. The Executive Engineer inspected the quality of work and directed that the pace of construction should be further accelerated while ensuring improved standards.
CWPP&H ROADS DISTRICT KILLA SAIFULLAH
Cons. of Kazha Meerzai Bridge β KSF
Observations:
Construction of 6 piers and abutments completed.
9 girders cast and post-tensioned.
River protection works in progress.
Directives to Contractor:
Expedite and complete girder launching activities.
Ensure timely completion of all remaining works at the earliest.
Observations:
Construction of 6 piers and abutments completed.
9 girders cast and post-tensioned.
River protection works in progress.
Directives to Contractor:
Expedite and complete girder launching activities.